Stage 1 – Preparation and analysis -2 days

Activities

Duration (Days)

 Results

System analysis

1

  • Check system requirements
  • Define the required configuration / installation

Business area definition

1/2

  • Defining topics and themes for 2 Storyboards
  • Defining the data that will be visualized within the SAP Analytics Cloud

Kickstart meeting with the client

1/2

  • Clarification of the approach, assumptions and expectations
  • Planning of resources, time and activities

 

Stage 2 – Development – 7 days

Activities Duration (Days)

 Results

Architectural and functionals installations

1

  • Installing and configuring the necessary data access tools
  • Data access testing

Creation of Data Models

3

  • Consumption of existing data models using a direct connection (Live connection)

  • Creating new data models, which will be used to create the visualizations defined in Phase 1

Creation of Storyboards

3

  • Development of the visualizations defined in Phase 1
  • Using the “Smart Discovery” function as an additional analysis tool

 

Stage 3 - Implementation – 1 day

Activities

Duration (Days)

Resuts

Virtual project presentation meeting

1

  • Presentation of the models and visualizations development within the project
  • Instructions for using of the developed analytics
  • Discussion and next steps

Support and warranty

30

  • Correction of any inaccuracies in the developed models and visualizations within 30 days after the project delivery

 